Brighton Hill roundabout will be experiencing further lane closures this week.
The roundabout improvement scheme will result in lane closures, which will be in place on the following dates and times:
From March 20 from 5am, through to 8pm on March 21, the exit lane from the roundabout onto The Harrow Way and the approach lanes to the roundabout from Brighton Way will be closed.
The approach lane to the roundabout from Western Way and the exit lanes from the roundabout onto Old Winchester Road will be closed from March 22 from 5am, until 8pm on March 23. Signed diversions will be in place.
The council said these lane closures are required to install drainage and undertake resurfacing works across the entries and exits at the roundabout. The works are weather dependent, and further notification will be given should there be any significant change to times or dates.
More information on the roundabout improvement scheme can be found at hants.gov.uk/transport/transportschemes/A30brightonhillroundabout.
For highways issues requiring urgent attention, Call 0300 555 1388 between 8:30am to 5pm, Monday to Friday, or phone 101 outside of office hours.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel